Prequalification for electromechanical equipment for Búrfell Extension Hydro Electric Plant

Landsvirkjun

Landsvirkjun announces the issue of prequalification document no. 20194, for the purpose of selecting contractors for the execution of works involving the electromechanical equipment of the Búrfell Extension Hydroelectric Plant.
The work consists of design, manufacture, installation and commissioning of one 100 MW generating unit, and related equipment. The construction of the plant is scheduled to start in the first half of 2016, and electricity production to start in April 2018.
Landsvirkjun plans to issue the tender documents in September 2015, available to those applicants only who qualify in this prequalification process.
The prequalification documents will be available on Landsvirkjun's electronic tender website, http://utbod.lv.is, by Tuesday, 2.6.2015.

Lokafrestur

Lokafrestur móttöku tilboða var 2015-07-14. Innkaupin voru birt 2015-06-01.

Seljendur

Eftirfarandi seljendur eru nefndir í veitingarákvörðunum eða öðrum útboðsgögnum:

Hver? Hvað? Hvar?
Saga innkaupa
Dagsetning Skjal
2015-06-01 Útboðsauglýsing
2015-07-07 Viðbótarupplýsingar
2016-03-30 Tilkynning um veitingu samnings
Útboðsauglýsing (2015-06-01)
Hlutur
Umfang innkaupanna
Heiti: Electrical machinery, apparatus, equipment and consumables; lighting
Magn eða umfang: See the Prequalification documents.
Lýsigögn tilkynningar
Upprunalegt tungumál: enska 🗣️
Tegund skjals: Útboðsauglýsing
Eðli samnings: Verk
Reglugerð: Annað
Sameiginlegur innkaupaorðaforði (CPV)
Kóði: Rafvélar, tæki, búnaður og rekstrarvörur; lýsing 📦

Ferli
Tegund ferlis: Opið útboð
Tegund tilboðs: Ekki tilgreint
Matsforsendur
Hagkvæmasta tilboðið

Kaupandi
Auðkenni
Land: Ísland 🇮🇸
Tegund veitandi yfirvalds: Veitustofnun
Heiti veitandi yfirvalds: Landsvirkjun
Póstföng: Haaleitisbraut 68
Póstnúmer: 103
Póstbær: Reykjavik
Tengiliður
Vefslóð: http://www.landsvirkjun.is 🌏
Tölvupóstur: innkaup@lv.is 📧
Sími: +354 5159000 📞
Fax: +354 5159006 📠

Tilvísun
Dagsetningar
Sendingardagsetning: 2015-06-01 📅
Lokafrestur fyrir framlag: 2015-07-14 📅
Birtingardagsetning: 2015-06-05 📅
Auðkenni
Tilkynningarnúmer: 2015/S 107-194963
OJ-S útgáfa: 107

Hlutur
Umfang innkaupanna
Stutt lýsing:
Landsvirkjun announces the issue of prequalification document no. 20194, for the purpose of selecting contractors for the execution of works involving the electromechanical equipment of the Búrfell Extension Hydroelectric Plant.
The work consists of design, manufacture, installation and commissioning of one 100 MW generating unit, and related equipment. The construction of the plant is scheduled to start in the first half of 2016, and electricity production to start in April 2018.
Sýna meira
Landsvirkjun plans to issue the tender documents in September 2015, available to those applicants only who qualify in this prequalification process.
The prequalification documents will be available on Landsvirkjun's electronic tender website, http://utbod.lv.is, by Tuesday, 2.6.2015.
Tilvísunarnúmer: 20194
Framkvæmdarstaður
Aðalstaður eða framkvæmdarstaður: Búrfell Hydropower station. Aprox. 100 km from Reykjavík.

Lagalegar, efnahagslegar, fjárhagslegar og tæknilegar upplýsingar
Skilyrði fyrir þátttöku
Hæfi til að stunda starfsemina: See the Prequalification documents.
Efnahagsleg og fjárhagsleg staða: See the Prequalification documents.
Tæknileg og fagleg geta: See the Prequalification documents.
Framkvæmd samnings
Tilskildar tryggingar og ábyrgðir: See the Prequalification documents.
Helstu fjármögnunarskilyrði og greiðslufyrirkomulag og/eða tilvísun í viðeigandi ákvæði sem þau falla undir: See the Prequalification documents.
Réttarform sem hópur rekstraraðila sem samningurinn er veittur skal taka: See the Prequalification documents.

Ferli
Gildistími tilboða: 90 dagar
Opnunardagur tilboða: 2015-07-14 📅
Upplýsingar um heimila einstaklinga og opnunarferli: Prequalification applicants, and their authorised representatives.
Tungumál
Önnur tungumál: Icelandic.

Kaupandi
Tengiliður
Tengiliður: Mr Bjarni Jakob Gíslason
Vefslóð: www.landsvirkjun.is 🌏
Vefslóð fyrir þátttöku: http://utbod.lv.is/is/ 🌏
Heimild: OJS 2015/S 107-194963 (2015-06-01)
Viðbótarupplýsingar (2015-07-07)
Hlutur
Lýsigögn tilkynningar
Tegund skjals: Viðbótarupplýsingar

Tilvísun
Dagsetningar
Sendingardagsetning: 2015-07-07 📅
Lokafrestur fyrir framlag: 2015-07-28 📅
Birtingardagsetning: 2015-07-10 📅
Auðkenni
Tilkynningarnúmer: 2015/S 131-241628
Vísar í tilkynningu: 2015/S 107-194963
OJ-S útgáfa: 131
Heimild: OJS 2015/S 131-241628 (2015-07-07)
Tilkynning um veitingu samnings (2016-03-30)
Hlutur
Umfang innkaupanna
Heildarvirði innkaupanna: 34 738 413 💰
Lýsigögn tilkynningar
Tegund skjals: Tilkynning um veitingu samnings
Reglugerð: Evrópska efnahagssvæðið (EES)

Ferli
Tegund tilboðs: Á ekki við

Tilvísun
Dagsetningar
Sendingardagsetning: 2016-03-30 📅
Birtingardagsetning: 2016-03-31 📅
Auðkenni
Tilkynningarnúmer: 2016/S 063-109601
OJ-S útgáfa: 63
Viðbótarupplýsingar
Landsvirkjun advertised the Pre-qualification for electromechanical equipment for Búrfell Extension Hydro Electric Plant on the TED on the 1.6.2015. 4 companies participated in the Pre-qualification and 3 companies were evaluated eligible to submit bids.
Sýna meira

Hlutur
Framkvæmdarstaður
Aðalstaður eða framkvæmdarstaður: Búrfell Hydropower station. Approx. 100 km from Reykjavík.

Tilvísun
Dagsetningar
Birtingardagsetning: 2015-07-07 📅
Auðkenni
Tilkynningarnúmer í OJ S: 2015/S 131-241628
Heimild: OJS 2016/S 063-109601 (2016-03-30)